Project Status

Phase 1 (Mckinney Street to hickory street and oak street from oakland street to uprr)

Phase 2 (I-35E to Scripture)

Project Background

This multi-phase project will accommodate growth, improve drainage systems and repair the pavement along the project area. Phase 1 includes drainage improvements and pavement repair along the Union Pacific Railroad (UPRR) from Mckinney Street to Hickory Street and on Oak Street from Oakland Street to the UPRR. Phase 2 will include similar improvements including drainage upgrades and pavement repair along the UPRR ROW from Hickory Street to Mulberry Street, Mulberry Street from the UPRR to Russell Street, and on Sycamore Street from Industrial Street to Bell Street. Construction is expected to begin after the design is complete. 

Project Updates

December 22: A notice to proceed for construction activities has been issued for Phase 1 of this project. Construction for Phase 1 (Oak Street from Oakland Street to the UPRR) is expected to begin in the coming weeks. Construction for Phase 1 is currently expected to be complete by September 2021.

The design for Phase 2 is continuing to progress and is expected to be complete by January 2021. Right-of-way agreements are required for this phase of the project and may impact the tentative timeline. Following the completion of the design phase, the project will begin the bid/advertise/award phase.