Capital Improvement Program

As Denton grows, the City continues to invest in important infrastructure to maintain and improve mobility, health and safety, and quality of life for residents and visitors. The Denton Capital Improvement Program advances many different projects over a number of years, including voter-approved bond projects; water and wastewater construction projects, and electric system improvements, among others.

General Obligation Bond Programs

The following capital improvement funding was authorized by voters as part of the 2012 and 2014 bond programs:

  • $82,110,000 for street improvements (2012 and 2014)
  • $16,565,000 for public safety facilities (2014)
  • $8,545,000 for stormwater drainage and flood control improvements (2014)
  • $11,355,000 for park system improvements (2014)

In an effort to minimize the impact on the tax rate, the City plans to issue these bonds in increments over a six-year period, with the full amount issued by 2020. Progress on the implementation of the bond program is reported in the City's quarterly financial reports.

CIP & CURRENT PROJECTS

  • Bonnie Brae Street South
    This will widen existing Bonnie Brae St. from two lanes to a divided four lane road between Vintage Blvd. and I-35E; and will widen Vintage Blvd. from two lanes to a divided six lane road from the I-35W Frontage Rd. to US 377. 

    View project background and current status here.

    Estimated Cost: $64 million

    Estimated Schedule:
    Phase 1: July 2017 to July 2019
    Phase 2: 2018 to 2020
    Phase 3: 2019 to 2021
    BonnieBraePhasingMap.jpg
    021318-pic-2.JPG
  • Mayhill Road
    This will widen Mayhill Rd. from two lanes to a divided four lane road (ultimately six lanes) between US 380 and Edwards Rd.

    View project background and current status here.

    Estimated Cost: $57.3 million

    Estimated Schedule: September 2017 to March 2020
    Pecan-Creek-9.JPG
     
    150-00-6.JPG
  • Magnolia Drive Drainage Project
    This is Phase II of the project that will:
    • Construct new box culverts on Hinkle Dr. and Windsor Dr. from Pecan Creek Rd. to Windsor Dr.
    • Reconstruct the asphalt pavement between the existing curb and gutter on Hinkle Dr. between University Dr. and Windsor Dr., and on Windsor Dr. between Hinkle Dr. and N Elm St.
    • Remove and reconstruct concrete curb and gutter where required
    View project background and current status​ here.

    Estimated Cost: $7.2 million

    Estimated Schedule: December 2018 to December 2019
    Magnolia-Drainage-Map-032818.PNG
  • Eagle Drive Drainage Phase II
    This will install 500 linear feet of box culvert near Eagle Dr. between Myrtle St. and Elm St.

    View project background and current status​ here.

    Estimated Cost: $2.54 million

    Estimated Schedule: August 2018 to August 2019
    Eagle-Drainage-Map.PNG
  • Pecan Creek Tributary Four Drainage Improvements
    Phases I and II will install approximately 1,500 linear feet of box culvert along the Pecan Creek Tributary 4 (PEC 4) Upper Tributary between Wainwright St. and Prairie St. This also includes water and wastewater replacements along Elm St. and Locust St. between Eagle Dr. and Hickory St.

    Phases III and IV will install approximately 2,700 linear feet of box culvert along the PEC 4 Upper Tributary between Prairie St. and Mulberry St.

    View project background and current status​ here.

    Estimated Cost: $21.2 million
     
    PEC4-(1).jpg
    Estimated Schedule: 
    Phases I & II: December 2018 to 2020
    Phases III & IV: 2021 to 2023

     
  • Hickory Creek Road West
    Construction will widen Hickory Creek Road from two lanes to four lanes between Teasley Lane and Riverpass Drive.

    View project background and current status​ here.

    Estimated Cost: $6.2 million

    Estimated Schedule: December 2018 - December 2019

    HickoryCreek.JPG
  • North South Water Main Phase II (Near Bonnie Brae St.)
    This will install approximately 10,000 linear feet of 36-inch and 42-inch water mains along Bonnie Brae St. between Roselawn Drive and I-35E.

    Estimated Cost: $8.1 million

    Estimated Schedule: April 2019 - March 2020

    NorthSouth.JPG
  • G. Roland Vela Athletic Complex
    The G. Roland Vela Athletic Complex will include four adult size multi-purpose athletic fields. The fields will be lighted and fenced and can accommodate active sports such as soccer, rugby, and football. The complex will also include a concession stand and restroom facilities, small and large pavilion areas, and a playground. The complex is funded primarily through voter approved bond packages, park dedication funds, project savings, and general funds.

    View project background and current status​ here.

    Estimated Cost: $6 million 

    Estimated Schedule: Expected Completion in Spring 2019
     
    Vela.JPG
  • 2019 Streets Reconstruction Project

    The City of Denton has several reconstruction projects planned to maintain the overall health of our transportation and utility infrastructure network. The 2019 Streets Reconstruction Project will include reconstruction of the following four roadways:

    • Windsor Drive, from N. Locust Stree to east of Old North Road
    • Scripture Street from Thomas Street to Jagoe Street
    • Thomas Street from Panhandle Street to Oak Street
    • Hercules Lane from N. Locust Street to Sherman Drive


    View project background and current status​ here.

    Estimated Cost: $12.5 Million 

    Estimated Schedule: Expected Completion in Winter 2021

    Vela.JPG

  • Hickory Street

    The Hickory Street project includes upgrading the roadway, water, wastewater, gas, and electric utilities in the area. The reconstruction of Hickory Street (Bonnie Brae to Carroll) is expected to be complete by fall 2019.

    View project background and current status​ here.

    Estimated Cost:  

    Estimated Schedule: Expected Completion in Fall 2019

  • McKinney Street Widening Project

    The McKinney Street project will widen McKinney Street from a two-lane rural roadway to a six-lane urban roadway from South Woodrow Lane to Grissom Road. The project is expected to be complete by November 2020.

    View project background and current status​ here.

    Estimated Cost: $31.25 million

    Estimated Schedule: Expected Completion in Winter 2020

     