[Skip to page content]
City of Denton logo stacked
X icon

Project Status



Currently, TxDOT crews are constructing the Brinker Road and Loop 288 bridge traffic rail and wall. IH-35E northbound main lanes are being paved and conrete driveways northound Frontage Road are being constructed.

Project Background

To accommodate mobility needs, I-35E is being expanded. When construction is complete, motorists will enjoy expanded lane capacity on I-35E and much improved mobility through the Loop 288/Lillian Miller, Brinker Road, and Mayhill Road underpasses. Visit keepitmovingdallas.com for additional information.

Project Updates

November 7: Weather permitting, the Texas Department of Transportation (TxDOT) will implement a new traffic pattern on the southbound Interstate 35E (I-35E) frontage road from Loop 288 to Mayhill Road beginning at 9 a.m. on Friday, November 8. Traffic on the frontage road will be shifted onto the newly constructed lanes. Once traffic is shifted, the remainder of the frontage road will be constructed. Message boards will be placed to alert drivers of the shift. Motorists should expect delays and seek alternate routes, if possible.
 
------
November 1: Weather permitting, Texas Department of Transportation (TxDOT) will have various north and southbound lane closures in place overnight from 9:00 P.M. to 6:00 A.M. on I-35E from Loop 288 to Mayhill Road beginning Sunday, November 3. The temporary lane closures will allow crews to safely mill and pave, place large signs, and remove barriers. TxDOT expects the nightly closures to last several days and will provide updates as work progresses. Message boards will be placed to alert drivers of the temporary lane closures. Motorists should expect delays and seek alternate routes, if possible. For updates on these road improvements and others, visit www.DriveTexas.org
 
------

October 8:  A contractor for Texas Department of Transportation (TxDOT) will begin construction for the installation of traffic signals at the I-35E and Brinker interchange. The installation will entail temporary span wire traffic signals and TxDOT will replace the temporary signals with a permanent signal at a later time. The signals are being installed to safely and efficiently move traffic on Brinker Road at the I-35E Frontage Road interchange. To allow crews safely complete the installation, lane closures will be in place during construction but traffic control plans will be developed to cause minimal impacts to traffic. 
------

October 1: Weather permitting, the Texas Department of Transportation (TxDOT) will begin reducing lanes on southbound Interstate 35E (I-35E) between the Loop 288 exit ramp and the Mayhill Road overpass at 10 p.m. on Wednesday, Oct. 2 in order to complete the transition to the newly constructed mainlanes by 6 a.m. on Thursday, Oct. 3. Exit 462 to State School Road/Mayhill Road will reopen at this time. Crews will begin work on the median barrier and centerline paving after the traffic switch. Message boards will be placed to alert drivers of the closures. Motorists should expect delays and seek alternate routes, if possible. For updates on these road improvements and others, visit www.DriveTexas.org
------
 
September 15: Crews are treating the recently paved southbound main lanes/ Brinker Road, removing the paving on Loop 288, completing drainage along Loop 288/southbound Frontage Road, and paving the southbound main lanes. The opening of the Brinker interchange is dependent on the installation of traffic signal lights and may occur before December 2019. 
------

August 6: Tonight, TxDOT crews will begin construction for the asphalt paving of the southbound main lanes. To address safety concerns, TxDOT will install new signal lights at the Brinker interchange. To allow crews to safely complete the installations, the interchange completion date has been updated to December. 
------
July 17: Weather permitting, TxDOT anticipates opening the Brinker interchange to traffic along with the new exit ramp by the end of September. 
------
June 6: Beginning, 9 p.m. Friday, June 7, Texas Department of Transportation (TxDOT) will temporarily close all main lanes of the Loop 288 underpass at IH 35E. This closure will allow crews to safely complete the placement of bridge beams on the southbound side of the IH 35E bridge over Loop 288. 

Weather and contractor scheduling may impact the plan, but TxDOT expects to reopen all lanes by 6 a.m. Saturday, June 8. 
Motorists are encouraged to find alternate routes. Please use caution and expect potential delays if your route includes this area.
-----
March 26: Beginning, 9 p.m. Friday, March 29, Texas Department of Transportation (TxDOT) will temporarily close all main lanes of the Loop 288 underpass at Interstate 35E. This closure will allow crews to safely deconstruct the existing bridge on the southbound side of the I35E bridge over Loop 288, and to place drainage across Loop 288 on the northbound side. 

Weather and contractor scheduling may impact the plan, but TxDOT expects to reopen all lanes by 6 a.m. Monday, April 1. 

TxDOT will have signed detours for traffic on Loop 288, Lillian Miller Road and both Frontage Roads. Please use caution and expect potential delays if your route includes this area.
-----
March 15: Texas Department of Transportation (TxDOT) plans to shift traffic on IH35E to newly constructed lanes next week.  
  • Weather permitting, Tuesday, March 19 at 10 p.m., IH35E northbound main lane traffic will switch onto the newly constructed northbound main lanes.
  • Weather permitting, Wednesday, March 20 at 10 p.m., IH35E southbound main lane traffic will switch onto the newly constructed northbound main lanes. 
The IH35E southbound exit ramp to Mayhill/State School Road/FM 2499 will be closed after the traffic switch is completed. All traffic will be exiting at the Loop 288 exit southbound to access Mayhill/State School Road/FM 2499. A new IH35E southbound exit ramp is scheduled to be constructed and opened within a week after the closure. TxDOT will notify the City of Denton regarding the planned opening of the new ramp and updates will be shared.

Please use caution in construction areas, adhere to posted construction signage, and expect potential delays if your route includes these areas..