Road and Utility Projects

Road and utility projects make up the majority of the City's Capital Improvement Program (CIP), but the CIP also includes regular upgrades, maintenance, and replacements. To maintain the overall health of our transportation and utility infrastructure network, existing roads and underground utility systems have to be reconstructed or replaced when they reach the end of their useful life. The projects listed below are the ongoing and upcoming projects that you can expect throughout 2019. All project schedules and timelines are subject to change.

Amherst Drive
Street construction to improve the condition of Amherst Drive from Fordham to Malone is expected to begin in the second quarter of 2019. Signage will be posted to alert motorists of temporary closures and parking restrictions. 

Atlas Drive
This improvement project requires streets, water, and wastewater improvements. Work is underway to reconstruct the wastewater main from Redstone to Hercules. Before wastewater pipe defects cause significant wastewater flow restrictions, they are replaced with a new, strong plastic pipe.  You may see crews work in an open trench, lowering each pipe segment into place, or you may also see them operate a “pipe bursting” machine, which drags new pipe in through a small pit while increasing the size of the pipe channel.  When the process is done, you will have a brand-new pipe with decades of use ahead. Crews from the Water Department are expected follow. 

Avenue A
The new University of North Texas residence hall construction is well underway and is expected to be complete in the first quarter of 2019.  It will feature pod-style student communities, private restrooms and Living Learning Communities. Currently, crews have closed Maple and Eagle southbound lanes during this phase of construction. 

Avenue B
This streets improvements project is from Margie to Underwood and is expected to begin in the first quarter of 2019.

Avenue C
This streets improvements project will include reconstruction of Avenue C from Mulberry Street to Oak Street. Crews will mill off some or all of the existing driving surface and replace the removed portion with a new driving surface. Once complete, the improvements will extend the life of Avenue C by an additional 10 years.

Avenue H
To improve the condition of Avenue H, Street Department crews are expected to begin construction from Louise to Prairie in the second quarter of 2019.  

Bernard Street
This street and wastewater improvement project spans from Hickory to Fannin. Work is underway from Fannin to W. Chestnut. During this time there will be no parking on the street and there will be limited access to driveways while crews are present. 

Bonnie Brae Street
To accommodate mobility needs, this major City project will expand Bonnie Brae St. from a two-lane undivided road to a divided four-lane road between Vintage Blvd. and I-35E. This project will also widen Vintage Blvd. from two lanes to a six-lane divided roadway from I-35W Frontage Rd. to US 377.

Bowling Green Street
This ongoing project includes water and street improvements. The water improvements include replacing the water main and the streets improvements include the reconstruction of the street. Due to the deteriorating condition of the asphalt and subgrade, reconstruction will include damaged concrete replacement (curb, valley gutters, driveways, etc.), removal of asphalt, stabilization of subgrade and installation of new asphalt pavement. Crews recently completed water service improvements from Georgetown to Auburn and street repairs are scheduled to begin late February. During this time, the street will close daily while crews are present and re-open at the end of each day.

Castle Lane
Due to the deteriorating condition of the road, crews from the Streets Department are currently reconstructing from Wilsonwood to the southern dead end. During this time, signage will be posted to alert motorists of the street closure and parking restrictions.

Dallas Drive
Construction to improve the turn lane from the intersection of Dallas Drive to Teasley Lane are underway. During this time, signage will be posted to alert motorists of the temporary lane closure. 

Eagle Drive
As part of the ongoing Eagle Drive Drainage Project, drainage and water improvements from Elm to Carroll are currently underway on Eagle Drive. During this time, signage will be posted to alert motorists of the temporary street closure in place. 

E. McKinney St.
This street improvement project will include the addition of a shoulder for a new turning lane, road restriping, and a mill and overlay of the roadway. During off-peak traffic hours, crews will close one lane of E. McKinney St. Traffic control flaggers will be in place from 9am to 4pm to manage the temporary one lane closure. 

Hickory Creek Road
Projects are underway to improve the safety of Hickory Creek Road by the City of Denton, Denton County, and TxDOT. Denton County will close Hickory Creek Road to thru traffic from FM 1830/Country Club Road to Riverpass Drive to complete guardrail installation. During this time, signage will be posted to alert motorists of the temporary closure.

Hickory Street
The reconstruction of Hickory Street (Bonnie Brae to Carroll) is expected to be complete by fall 2019. The project includes upgrading the roadway, water, wastewater, gas, and electric utilities in the area. Currently, Atmos Gas is working in the area between Avenue B and Welch. 

Fannin Street
Construction to improve the street and water services are planned to begin in the second quarter of 2019 from Welch to Beatty. 

Forrestridge Drive
Construction to improve the street are planned to begin in the first quarter of 2019 from Hobson to Highview.

Foxcroft Circle
Wastewater improvements from East of Old North to Emerson and Northcrest to Archer Trail are expected to begin in the second quarter of 2019.

Fulton Street
This ongoing project requires streets, water, and wastewater improvements from Congress to W. Oak. Work is currently underway to reconstruct the wastewater main from Congress to Gregg. This is the final phase of wastewater and street improvements will follow.

Greeenway/Augusta
Street construction to improve the condition of Amherst Drive from Fordham to Malone is expected to begin in the second quarter of Due to the deteriorating condition of the road, crews from the Streets and Wastewater Departments will begin improvements from Windsor Farms to the dead end in the fourth quarter of 2019. Signage will be posted to alert motorists of the temporary lane closure and parking restrictions

Hercules Lane
This improvement project requires upgrades of the street and water services from Sherman to Meadow. Currently, water improvements are underway from Sherman to Sun Valley. 

Highview Circle
Street improvements are expected to begin in the first quarter of 2019 along the full extent of Highview Circle to improve the road condition.

Hill Alley
Water service improvements are scheduled to begin in the second quarter of 2019 from Robertson to Martin.

Hillcrest Street
This ongoing project includes wastewater and street improvements from Emerson to Scripture. Crews are currently reconstructing the wastewater main from Crescent to Emory. Signage is posted to alert motorists of the temporary lane closure and parking restrictions 

Hinkle Drive
As part of the larger Magnolia Drainage Project, crews are scheduled to begin improvements to the storm water system from University to Windsor in the second quarter of 2019. Signage will be posted to alert motorists of the temporary lane closure and parking restrictions.

Jannie Street
This street construction project will include water tap improvements, excavation, and street repairs.

Johnson Street
Street and water improvements are scheduled for the second quarter of 2019 from Mill to Douglas Collins to Daughtery. Signage will be posted to alert motorists of the temporary lane closure.

Kendolph Drive
This ongoing project includes street, water, and wastewater improvements from I-35E to Willowwood St. Currently, crews are making wastewater improvements. A daily street closure is in place, re-opening to traffic at the end of each day. Once wastewater improvements are complete, the Streets Department will follow to repave the street. Signage is posted to alert motorists of the closure and parking restrictions.


Kerley Street
This project includes improvements to the street, water and wastewater services from Duncan to Shady Oaks. Currently, crews from the Water Department are improving the water services and a daily street closure is in effect. At the end of each work day, the street is re-opened to traffic. Signage is posted to alert motorists of the closure and parking restrictions.

Kings Row
This ongoing project requires street, water and wastewater improvements from Stuart to Sherman. Crews are currently replacing the curb and gutter from Yellowstone to Sherman. Signage is posted to alert motorists of the temporary lane closure and parking restrictions.

Laguna Street
Street improvements are ongoing from Yellowstone to Sherman. Crews are currently replacing the curb and gutter from Yellowstone to Sherman. Signage is posted to alert motorists of the temporary lane closure and parking restrictions. 

Lipizzan Drive
Crews are making street panel repairs on Lipizzan Drive from Wheeler Ridge Dr. to Thoroughbred Trail. Signage is posted to alert motorists of the temporary lane closure. 

Manhattan  Drive
This ongoing project requires street, water, and wastewater improvements from Yellowstone to Sherman. Currently, crews are replacing the curb and gutter by removing the failed sections of curb and installing new concrete. The new concrete has to cure for a period of 7 to 14 days before it can be opened to traffic. This is done to allow the concrete to reach sufficient strength to support traffic. Signage is posted to alert motorists of the temporary lane closure and parking restrictions.  

Mayhill Road
To alleviate traffic congestion on Mayhill Road, this major City project will expand Mayhill from a two-lane undivided road to a divided four-lane road. Crews are currently working from US 380 to Edwards.

McKinney Street
Utility improvements are underway on E. Mckinney Street from Woodrow Lane to Jannie Street. Signage is posted to alert motorists of the temporary outside lane closure and parking restrictions. 

Mill Street
This project includes street, water and drainage improvements scheduled to begin in the second quarter of 2019 from Wye to Industrial.

Mistywood Lane/Royal Lane
This ongoing project requires street, water, wastewater and drainage improvements from Woodhaven to Jamestown including Royal and Rockwood. Crews are currently improving the drainage system from Rockwood to Jamestown. Water improvements are scheduled to follow in the second quarter of 2019. Signage is posted to alert motorists of the intermittent street closure and parking restrictions.

Mulberry Street
This street and water improvement project is from Bernard to Cedar and expected to begin in the third quarter of 2019.

Myrtle Street
As part of the ongoing Eagle Drive Drainage Project, drainage and water improvements from Eagle to Maple are currently underway on Myrtle Street. During this time, signage will be posted to alert motorists of the temporary street closure in place. 

Northwood Terrace
In the second quarter of 2019, the City is scheduled to begin a series of improvements including street, water and wastewater from the northern extent to Edgewood Place. 

Orr Street
Street and water improvements are scheduled to begin in the second quarter of 2019 from Elm to Locust. Signage will be posted to alert motorists of the lane closures and parking restrictions. 

Paisley Street
Sidewalk repairs are currently underway for this ongoing street improvement project from Frame to Ruddell. During this time, there will be street parking. During this time, there will be no parking on the street and there will be limited access to driveways while crews are present.

Panhandle Street
Street resurfacing and curb and gutter replacements are expected to begin in the first quarter of 2019 from Aileen to Malone. The process starts with the replacement of failed curb and gutter, driveway, radius, and valley gutter. Crews will follow with milling the old asphalt surface and apply new asphalt. Signage will be posted to alert motorists of the temporary lane closure and parking restrictions. 

Quail Ridge Drive
This project includes street and water improvements scheduled to begin in the third quarter of 2019 from Cooper Branch to La Paloma. 

Roberts/Woodland/Brown
Street and water improvements are scheduled to begin in the third quarter of 2019 on Roberts (from Brown to Brown) and Woodland (from Brown to Cherrywood) Signage will be posted to alert motorists of the lane closure and parking restrictions. 

Robson Ranch
Wastewater improvements from the easement between Robson Ranch and I-35W are scheduled to begin in the third quarter of 2019. 

Sagewood Street
This street improvement project from Meadow to Peartree is expected to begin in the third quarter of 2019. 

Sandy Creek Drive
To improve the street condition and wastewater infrastructure from Angeline Bend to Sandy Creek, construction is scheduled to begin in the third quarter of 2019.

Scripture Street
This street improvement project from Thomas to Jagoe is schduled to begin in the second quarter of 2019.

Sheraton  Road
Street improvements are scheduled to begin the fourth quarter of 2019 from Imperial to Sun Valley. 

Sierra Drive
Curb and gutter replacements are currently underway from Yellowstone to Sherman. This improvement project also includes Water and wastewater construction phases are scheduled to follow. 

Silent Star Lane
This improvement project will replace the concrete street panels and repair the sidewalk on Silent Start Lane from Winding Stream Drive to Montecito Drive.

Spencer Drive
Concrete street panels repairs are currently underway in the westbound lane from S. Woodrow Lane to the Denton Municipal Electric utility yard entrance. The westbound lane will be temporarily closed as crews repair the two panels.

Springtree Street
This street construction project is a part of the current E. McKinney Street improvement project. Crews are adding an additional turning lane and making street improvements.

Stella Street/Avenue H
Curb and gutter replacements are currently underway from Yellowstone to Sherman. This improvement project also includes Water and wastewater construction phases are scheduled to follow. 

Thomas Street
This street improvement project from Panhandle to W. Oak is scheduled to begin in the first quarter of 2019. Crews will be improving the quality of the street and signage will be posted to alert motorists of closures and parking restrictions.

Uland Street
This project includes street and wastewater improvements from Railroad to Rose. Crews are scheduled to begin these improvements in the second quarter of 2019.

Wayne Street 
Ongoing construction is underway from Boyd to Monzingo to improve the street and water services.

Wellington Drive
Wastewater improvements northwest of Sherman are scheduled to begin in the first quarter of 2019.

Westgate Drive
Street improvements are expected to begin in the third quarter of 2019 from Fladger to Windsor.

Whitney Court
Street improvements along the full extent of Whitney Court are scheduled to begin in the second quarter of 2019. Signage will be posted to alert motorists of the temporary street closure and parking restrictions.

Windsor Drive
This street improvement project from Hinkle to Elm is scheduled to begin in the second quarter of 2019.

Woodbrook Street
This street improvement project from Southridge to Hollyhill is scheduled to begin in the second quarter of 2019.

Yellowstone Place
This project includes street, water and wastewater improvements from Kings Row to Monterrey. Crews from the Streets Department are scheduled to begin curb and gutter replacements in the first quarter of 2019.