[Skip to page content]
City of Denton logo stacked
X icon
Home > Government > Strategic Initiatives > Improving Denton > Road and Utility Projects

Road and Utility Projects

Road and utility projects make up the majority of the City's Capital Improvement Program (CIP), but the CIP also includes regular upgrades, maintenance, and replacements. To maintain the overall health of our transportation and utility infrastructure network, existing roads and underground utility systems have to be reconstructed or replaced when they reach the end of their useful life. The projects listed below are the ongoing and upcoming projects that you can expect throughout 2019. All project schedules and time lines are subject to change.

Amherst Drive
Street construction to improve the condition of Amherst Drive from Fordham to Malone is expected to begin in the second quarter of 2019. Signage will be posted to alert motorists of temporary closures and parking restrictions. 

Atlas Drive
This improvement project requires streets, water, and wastewater improvements. Work is underway to reconstruct the wastewater main from Redstone to Hercules. Before wastewater pipe defects cause significant wastewater flow restrictions, they are replaced with a new, strong plastic pipe.  You may see crews work in an open trench, lowering each pipe segment into place, or you may also see them operate a “pipe bursting” machine, which drags new pipe in through a small pit while increasing the size of the pipe channel.  When the process is done, you will have a brand-new pipe with decades of use ahead. Crews from the Water Department are expected to follow in March. 

Avenue A
The new University of North Texas residence hall construction is well underway and is expected to be complete in the first quarter of 2019.  It will feature pod-style student communities, private restrooms and Living Learning Communities. Currently, crews have closed Maple and Eagle southbound lanes during this phase of construction. 

Avenue B
This streets improvements project is from Margie to Underwood and is expected to begin in the first quarter of 2019.

Avenue C
This streets improvements project will include reconstruction of Avenue C from Mulberry Street to Oak Street. Crews will mill off some or all of the existing driving surface and replace the removed portion with a new driving surface. Once complete, the improvements will extend the life of Avenue C by an additional 10 years.

Avenue H
To improve the condition of Avenue H, Street Department crews are expected to begin construction from Louise to Prairie in the second quarter of 2019.  

Bell Avenue
This construction project will improve the intersection right turn-lane at the southeast corner of Bell Avenue and McKinney Street. The existing ramps will be removed and replaced with approved ADA ramps. During this time there will be no parking on the street and the northbound right turning lane will be temporarily closed while crews complete improvements and reopened each afternoon. 

Bernard Street
This street and wastewater improvement project spans from Hickory to Fannin. Work is underway from Fannin to W. Chestnut. During this time there will be no parking on the street and there will be limited access to driveways while crews are present. 

Blagg Road
Blagg Rd. from N. Mayhill Rd. to Geesling is closed to allow crews to safely continue bridge construction as part of the ongoing Mayhill Road widening capital improvement project. Signage will be posted to alert motorists of the closure and detour in place.

Bonnie Brae Street
To accommodate mobility needs, this major City project will expand Bonnie Brae St. from a two-lane undivided road to a divided four-lane road between Vintage Blvd. and I-35E. This project will also widen Vintage Blvd. from two lanes to a six-lane divided roadway from I-35W Frontage Rd. to US 377.

Bonnie Brae Street
This improvement project will include upgrades to the water lines in the area on S. Bonnie Brae Street from Highland Park to Willowwood Street as part of the North South Water Main Phase II captial improvement project. To allow crews to safely complete the improvements, a temporary lane closure will be in place. Signage is posted to alert motorists of the temporary closure and detour in place during this time. 

Bonnie Brae Street
Crews will be completing improvements on Bonnie Brae Street from University to Linden for new Rayzor Ranch developments. The improvements include tying into the back of the inlet with reinforced concrete pipe and constructing a culvert to the pond. Signage will be posted to alert motorists of the temporary lane closure in place to allow crews to safely complete construction.

Bowling Green Street
This ongoing project includes water and street improvements. The water improvements include replacing the water main and the streets improvements include the reconstruction of the street. Due to the deteriorating condition of the asphalt and subgrade, reconstruction will include damaged concrete replacement (curb, valley gutters, driveways, etc.), removal of asphalt, stabilization of subgrade and installation of new asphalt pavement. Crews recently completed water service improvements from Georgetown to Auburn and street repairs are scheduled to begin late February. During this time, the street will close daily while crews are present and re-open at the end of each day.

Carroll Boulevard
This improvement project includes concrete street panel and sidewalk repairs on Carroll Boulevard from Panhandle Street to Crescent Street. During this time, signage will be posted to alert motorists of the temporary lane closures and parking restrictions.

Castle Lane
Due to the deteriorating condition of the road, crews from the Streets Department are currently reconstructing from Wilsonwood to the southern dead end. During this time, signage will be posted to alert motorists of the street closure and parking restrictions.

Cedar Street
This improvement project will include the installation of water and wastewater services in the area on N. Cedar Street from W. Pecan Street to W. Oak Street. During this time, signage will be posted to alert motorists of the temporary street closure and detour in place.

Crestoak Place
This improvement project will include concrete curb and gutter replacements and street resurfacing on Crestoak Place from Liveoak Street to Oakridge Street. During this time, there will be no parking on the street while crews are present and signage will be posted to alert motorists of the temporary lane closure. 

Crestwood Place
This improvement project will include concrete curb and gutter replacements and street resurfacing on Crestwood Place from Liveoak Street to Edgewood Place. During this time, there will be no parking on the street while crews are present and signage will be posted to alert motorists of the temporary lane closure. 

Crestwood Place
This improvement project will include concrete curb and gutter replacements and street resurfacing on Crestoak Place from Greenwood Drive to Kayewood Drive. During this time, there will be no parking on the street while crews are present and signage will be posted to alert motorists of the temporary lane closure. 

Daisy  Drive
This improvement project will include concrete street panel and sidewalk repairs on Daisy Drive from Boxwood Drive to Sweetgum Drive. During this time, signage will be posted to alert motorists of the temporary lane closure on Daisy Drive and parking restrictions. 

Dallas Drive
Construction to improve the turn lane from the intersection of Dallas Drive to Teasley Lane are underway. Weather permitting, the project is projected to be completed June 2019. During this time, signage will be posted to alert motorists of the temporary lane closures and/or detours. 

Eagle Drive
As part of the ongoing Eagle Drive Drainage Project, drainage and water improvements from Elm to Carroll are currently underway on Eagle Drive. During this time, signage will be posted to alert motorists of the temporary street closure in place. 

Edgewood Place
This improvement project will include concrete curb and gutter replacements and street resurfacing on Crestoak Place from Oakridge Street to Crestwood Place. During this time, there will be no parking on the street while crews are present and signage will be posted to alert motorists of the temporary lane closure. 

Edgewood Place
This improvement project will include new sewer and water main installations on Edgewood Place from Northwood Terrace to Crestwood Place. During this time, temporary lane closures will be in place to allow crews to safely complete construction. Detours will be provided so residents maintain access to their homes. Crews will suspend the temporary lane closures from June 3 until June 19. During this time, residents will be able to safely travel in both lanes. Intermittent lane closures will be in place June 19 until the projects proposed completion date.

E. McKinney Street
This street improvement project will include the addition of a shoulder for a new turning lane, road re striping, and a mill and overlay of the roadway. During off-peak traffic hours, crews will close one lane of E. McKinney St. from Mack Drive to Bellaire Drive. Traffic control flaggers will be in place from 9am to 4pm to manage the temporary one lane closure. 

E. McKinney Street 
This sidewalk improvement project will include concrete sidewalk, partial curb and driveway replacement or installation, and ADA upgrades. During this time, signage will be posted to alert motorists of the temporary lane closure on E. McKinney Street from S. Austin Street to Oakland Street.

E. Sycamore Street 
Union Pacific Railroad will complete improvements to the railroad crossing located at E. Sycamore Street and just east of S. Bell Avenue. Improvements will include replacing the railroad ties, cribbing the crossing, and surfacing through the crossing. To allow crews to safely complete the project, during construction the crossing will be temporarily closed. 

Fannin Street
Construction to improve the street and water services are planned to begin in the second quarter of 2019 from Welch to Beatty. 

Forrestridge Drive
Construction to improve the street are planned to begin in the first quarter of 2019 from Hobson to Highview.

Foxcroft Circle
Wastewater improvements from East of Old North to Emerson and Northcrest to Archer Trail are expected to begin in the second quarter of 2019.

Fulton Street
This ongoing project requires streets, water, and wastewater improvements from Congress to W. Oak. Work is currently underway to reconstruct the wastewater main from Congress to Gregg. This is the final phase of wastewater and street improvements will follow.

Greeenway/Augusta
Street construction to improve the condition of Amherst Drive from Fordham to Malone is expected to begin in the second quarter of Due to the deteriorating condition of the road, crews from the Streets and Wastewater Departments will begin improvements from Windsor Farms to the dead end in the fourth quarter of 2019. Signage will be posted to alert motorists of the temporary lane closure and parking restrictions

Hann Street
This improvement project will include utility upgrades and new water line installation on Hann Street. To allow crews to safely complete construction, Hann Street from N. Locust Street to N. Austin Street will be temporarily closed to thru traffic. 

Hercules Lane
This improvement project will include water main replacement on Hercules Lane from Sherman Drive to Stuart Road. During this time, Hercules Lane will be closed to thru traffic while crews are present and reopened at the end of each work day.

Heritage Trail
This improvement project will include street resurfacing, turn lane installation, and curb and gutter improvements at Heritage Trail from Linden Drive to W. University Drive.

Hickory Creek Road
The section of Hickory Creek Road between FM 1830 and Riverpass Drive underwent significant short-term improvements. This work included trimming trees to increase visibility and adding new guardrails, raised reflective pavement markers, new striping, and curve warning and guidance signs that illuminate when a vehicle approaches to improve safety. Review the latest project updates here.

Hickory Street
The reconstruction of Hickory Street (Bonnie Brae to Carroll) is expected to be complete by fall 2019. The project includes upgrading the roadway, water, wastewater, gas, and electric utilities in the area. Crews began street reconstruction from Avenue B to Fry Street and wastewater main replacement at the intersection of Fry Street. To allow crews to safely complete the improvements, a section of Hickory Street from Avenue B to Fry Street will be temporarily closed. Please use caution when traveling in the area and refer to the detour map provided for alternate routes.

Highview Circle
This project includes street reconstruction on Highview Court from Forrestridge Drive to Forrestride Drive. Crews will verify the depth of utility lines, replace the damaged concrete (curb, valley gutters, driveways, etc.), remove seven inches of asphalt, and install new asphalt pavement. During this time, there will be no parking on the street and limited access to driveways while crews are present. 

Highview Court
This project includes street reconstruction on Highview Court from Highview Circle to the dead end of the street. Crews will verify the depth of utility lines, replace the damaged concrete (curb, valley gutters, driveways, etc.), remove seven inches of asphalt, and install new asphalt pavement. During this time, there will be no parking on the street and limited access to driveways while crews are present. 

Hillcrest Street
This improvement project will upsize the wastewater main line and services for the area. Crews will also be installing new manholes to allow for better accessibility to maintain the pipes. During this time, there will be no parking on the street and traffic control will be in place on Hillcrest Street for the duration of the project. All residents will have access to their homes during this time.

Hill Alley
Water service improvements are scheduled to begin in the second quarter of 2019 from Robertson to Martin.

Hillcrest Street
This ongoing project includes wastewater and street improvements from Emerson to Scripture. Crews are currently reconstructing the wastewater main from Crescent to Emory. Signage is posted to alert motorists of the temporary lane closure and parking restrictions 

Hinkle Drive
As part of the larger Magnolia Drainage Project, crews are scheduled to begin improvements to the storm water system from University to Windsor in the second quarter of 2019. Signage will be posted to alert motorists of the temporary lane closure and parking restrictions.

Jannie Street
This street construction project will include water tap improvements, excavation, and street repairs.

Johnson Street
Street and water improvements are scheduled for the second quarter of 2019 from Mill to Douglas Collins to Daughtery. Signage will be posted to alert motorists of the temporary lane closure.

Kendolph Drive
This ongoing project includes street, water, and wastewater improvements from I-35E to Willowwood St. Wastewater improvements recently were completed and crews from the Streets Department are currently completing street repairs. Signage is posted to alert motorists of the temporary closure and parking restrictions.

Kerley Street
This project includes improvements to the street, water and wastewater services from Duncan to Shady Oaks. Currently, crews from the Wastewater Department are replacing the sewer main, upsizing its capacity, and installing a manhole. All service lines in poor condition will be replaced and cleanouts will be installed at the right of way. During this time, a temporary street closure is in place from Shady Oaks Drive to Minor Circle. Signage is posted to alert motorists of the temporary closures and detour via Duncan Street.

Kings Row
This ongoing project requires street, water and wastewater improvements from Stuart to Sherman. Crews are currently replacing the curb and gutter from Yellowstone to Sherman and completing street reconstruction on Yellowstone to Sherman and Stuart. Signage is posted to alert motorists of the temporary lane closure and parking restrictions.

Manhattan  Drive
This ongoing project requires street, water, and wastewater improvements from Yellowstone to Sherman. Currently, crews are replacing the curb and gutter by removing the failed sections of curb and installing new concrete. The new concrete has to cure for a period of 7 to 14 days before it can be opened to traffic. This is done to allow the concrete to reach sufficient strength to support traffic. Signage is posted to alert motorists of the temporary lane closure and parking restrictions.  

Mayhill Road
To alleviate traffic congestion on Mayhill Road, this major City project will expand Mayhill from a two-lane undivided road to a divided four-lane road. Crews are currently working from US 380 to Edwards.

McCormick Street
Beginning Monday, March 11, McCormick Street from Underwood Street to Avenue A will be closed permanently for construction. This closure will allow crews to begin utility work and construction of the new Fire Station 3 on the west side of McCormick Street. Underwood Street will remain open to Ave A and I-35E. Signage is posted to alert motorists of the closure and parking restrictions.

Mercedes Street
This improvement project will include concrete curb and gutter replacements and street resurfacing on Mercedes Street from Oakwood Drive to Willowwood Street. Signage is posted to alert motorists of the temporary street closure while crews are present and detour in place. The street will be reopened at the end of each day. 

McKinney Street
Utility improvements are underway on E. Mckinney Street from Woodrow Lane to Jannie Street. Signage is posted to alert motorists of the temporary outside lane closure and parking restrictions. 

Michial Street
This improvement project will include concrete curb and gutter replacements and street resurfacing on Michial Street from McCormick Street to Knight Street. Signage is posted to alert motorists of the temporary street closure while crews are present and detour in place. The street will be reopened at the end of each day. 

Mills Road
This improvement project will include the construction of a storm drain and inlets, relocation of the waterline in the area, and a new asphalt surface at the intersection of Mayhill Road and Mills Road. To allow crews to safely complete construction, Mills Road will have a temporary street closure in place during this time. Signage will be posted to alert motorists of the temporary street closure and detour on E. Mckinney Street and S. Trinity Street. 

Mill Street
This project includes street, water and drainage improvements scheduled to begin in the second quarter of 2019 from Wye to Industrial.

Morse Street
This project will include the installation of a waterline as part of the ongoing Mayhill road widening capital improvement project. Morse Street will be closed at the intersection of Mayhill Road to thru traffic to allow crews to safely complete construction. 

Mistywood Lane/Royal Lane
This ongoing project requires street, water, wastewater and drainage improvements from Woodhaven to Jamestown including Royal and Rockwood. Crews are currently improving the drainage system from Rockwood to Jamestown. Water improvements are scheduled to follow in the second quarter of 2019. Signage is posted to alert motorists of the intermittent street closure and parking restrictions.

Mulberry Street
This street and water improvement project is from Bernard to Cedar and expected to begin in the third quarter of 2019.

Mustang Drive
This street improvement project is from Sundown Blvd. to Palomino Ct and will include sidewalk and concrete street panel repairs. During this time, one lane will remain open to residents at all times, and there will be no parking permitted on the street.

Myrtle Street
As part of the ongoing Eagle Drive Drainage Project, drainage and water improvements from Eagle to Maple are currently underway on Myrtle Street. During this time, signage will be posted to alert motorists of the temporary street closure in place. 

Neff Street
This improvement project will include concrete curb and gutter replacements and street resurfacing on Neff Street from W. Collins Street to Greenlee Street. Signage is posted to alert motorists of the temporary street closure while crews are present and detour in place. The street will be reopened at the end of each day. 

North Texas Boulevard
Due to the deteriorating condition of the curb, crews will remove failed sections of curb and install new concrete on North Texas Boulevard from Prairie Street to Stella Street. To allow crews to safely complete the improvements, during this time the southbound lane will be temporarily closed while crews are present and there will be no parking on the street.

Northwood Terrace
This improvement project will include new sewer and water main installations on Northwood Terrace from the cul de sac to Edgewood Place. During this time, temporary lane closures will be in place to allow crews to safely complete construction. Detours will be provided so residents maintain access to their homes. Crews will suspend the temporary lane closures from June 3 until June 19. During this time, residents will be able to safely travel in both lanes. Intermittent lane closures will be in place June 19 until the projects proposed completion date.

Nottingham Drive
In the second quarter of 2019, the City is scheduled to begin a series of improvements including street, water and wastewater from the northern extent to Edgewood Place.

Orr Street
Street and water improvements are scheduled to begin in the second quarter of 2019 from Elm to Locust. Signage will be posted to alert motorists of the lane closures and parking restrictions. 

Paco Trail
Sidewalk repairs are currently underway on Paco Trail from N. Ruddell Street to the end of the cul de sac. During this time, there will be no parking on the street while crews are present and limited access to driveways.

Paisley Street
Sidewalk repairs are currently underway for this ongoing street improvement project from Frame to Ruddell. During this time, there will be no parking on the street while crews are present and there will be limited access to driveways.

Panhandle Street
Street resurfacing and curb and gutter replacements are expected to begin in the first quarter of 2019 from Aileen to Malone. The process starts with the replacement of failed curb and gutter, driveway, radius, and valley gutter. Crews will follow with milling the old asphalt surface and apply new asphalt. Signage will be posted to alert motorists of the temporary lane closure and parking restrictions. 

Peak Street
This improvement project will include concrete curb and gutter replacements and street resurfacing on Peak Street from Greenlee Street to Fannin Street. Signage is posted to alert motorists of the temporary street closure while crews are present and detour in place. The street will be reopened at the end of each day. 

Quail Ridge Drive
This project includes street and water improvements scheduled to begin in the third quarter of 2019 from Cooper Branch to La Paloma. 

Roberts/Woodland/Brown
Street and water improvements are scheduled to begin in the third quarter of 2019 on Roberts (from Brown to Brown) and Woodland (from Brown to Cherrywood) Signage will be posted to alert motorists of the lane closure and parking restrictions. 

Robson Ranch
Wastewater improvements from the easement between Robson Ranch and I-35W are scheduled to begin in the third quarter of 2019. 

Sagewood Street
This street improvement project from Meadow to Peartree is expected to begin in the third quarter of 2019. 

San Felipe Drive
This improvement project will include side walk repairs on San Felipe Drive from Willowick Circle to Chimney Rock Drive.

Sandy Creek Drive
To improve the street condition and wastewater infrastructure from Angeline Bend to Sandy Creek, construction is scheduled to begin in the third quarter of 2019.

Scripture Street
This street improvement project from Thomas to Jagoe is schduled to begin in the second quarter of 2019.

Shady Shores Road
This improvement project will involve concrete street panel replacement on W Shady Shores Road from Old US Hwy 77 to Swisher Road. The process includes crews barricading the failed sections of concrete pavement, removing the pavement and subgrade, and installing new concrete pavement.

Sheraton Road
This project includes street reconstruction on Sheraton Road from Sun Valley to Hercules. Crews will verify the depth of utility lines, replace the damaged concrete (curb, valley gutters, driveways, etc.), remove seven inches of asphalt, and install new asphalt pavement. During this time, there will be no parking on the street and limited access to driveways while crews are present.

Sheraton Place
This improvement project will involve street reconstruction on Sheraton Place from Sheraton Road to Buckingham Drive. Due to the deteriorating condition of the asphalt and subgrade, the street is in need of reconstruction. During this time, signage will be posted to alert residents of the temporary street closure.

Sherman Drive
This improvement project will include replacing the sewer main, upsize its capacity and the installation of a manhole on Sherman Drive from Monterey Lane to Stuart Road. All service lines in poor condition will be replaced and cleanouts will be installed at the right of way. To allow crews to safely complete the improvements, the southbound outside lane will be temporarily closed. Windsor Drive will be temporarily closed during construction while crews work in the intersection. Traffic will be detoured to Stuart Road then north back to Windsor Drive.

Silent Star Lane
This improvement project will replace the concrete street panels and repair the sidewalk on Silent Start Lane from Winding Stream Drive to Montecito Drive.

Springtree Street
This street construction project is a part of the current E. McKinney Street improvement project. Crews are adding an additional turning lane and making street improvements.

Stella Street/Avenue H
Curb and gutter replacements are currently underway from Yellowstone to Sherman. This improvement project also includes Water and wastewater construction phases are scheduled to follow. 

Thomas Street
This street improvement project from Panhandle to W. Oak is scheduled to begin in the first quarter of 2019. Crews will be improving the quality of the street and signage will be posted to alert motorists of closures and parking restrictions.

Uland Street
This project includes street and wastewater improvements from Railroad to Rose. Crews are scheduled to begin these improvements in the second quarter of 2019.

Wayne Street 
Ongoing construction is underway from Boyd to Monzingo to improve the street and water services.

Welch Street
This construction project will involve the installation of a fire line tap on S. Welch Street between Maple Street and Eagle Drive for a new housing development. During this time, there will be signage posted to alert motorists of the closure and detour.

Wellington Drive
Wastewater improvements northwest of Sherman are scheduled to begin in the first quarter of 2019.

Westgate Drive
Street improvements are expected to begin in the third quarter of 2019 from Fladger to Windsor.

Whitney Court
Street improvements along the full extent of Whitney Court are scheduled to begin in the second quarter of 2019. Signage will be posted to alert motorists of the temporary street closure and parking restrictions.

Windsor Drive
This street improvement project from Hinkle to Elm is scheduled to begin in the second quarter of 2019.

Woodbrook Street
This street improvement project from Southridge to Hollyhill is scheduled to begin in the second quarter of 2019.

Yellowstone Place
This project includes street, water and wastewater improvements from Kings Row to Monterrey. Crews from the Streets Department are scheduled to begin curb and gutter replacements in the first quarter of 2019.