Road and Utility Projects

Road and utility projects make up the majority of the City's Capital Improvement Program (CIP), but the CIP also includes regular upgrades, maintenance, and replacements. To maintain the overall health of our transportation and utility infrastructure network, existing roads and underground utility systems have to be reconstructed or replaced when they reach the end of their useful life. The projects listed below are the ongoing and upcoming projects that you can expect throughout 2019. Detour maps are included for planned projects that will require a complete street closure. All project schedules and time lines are subject to change.

Amherst Drive
Street construction to improve the condition of Amherst Drive from Fordham to Malone is expected to begin in the first quarter of 2020. Signage will be posted to alert motorists of temporary closures and parking restrictions. 

Atlas Drive
This improvement project requires streets, water, and wastewater improvements. Work is underway to reconstruct the wastewater main from Redstone to Hercules. Before wastewater pipe defects cause significant wastewater flow restrictions, they are replaced with a new, strong plastic pipe.  You may see crews work in an open trench, lowering each pipe segment into place, or you may also see them operate a “pipe bursting” machine, which drags new pipe in through a small pit while increasing the size of the pipe channel.  When the process is done, you will have a brand-new pipe with decades of use ahead.

Avenue B
This streets improvements project is from Margie to Underwood and is expected to begin in the first quarter of 2020.

Avenue H
To improve the condition of Avenue H, Street Department crews are expected to begin construction from Louise to Prairie in the fourth quarter of 2020.  

Bell Avenue
This construction project will improve the intersection right turn-lane at the southeast corner of Bell Avenue and McKinney Street. The existing ramps have been removed and replaced with approved ADA ramps. There are no current traffic impacts, and final improvements to the street lights in the area will be completed to wrap up this project.

Bernard Street
Street and wastewater improvements are scheduled for the third quarter of 2020 on Bernard Street from Hickory Street to Fannin Street.

Blagg Road (See detour map)
Blagg Rd. from N. Mayhill Rd. to Geesling is closed to allow crews to safely continue bridge construction as part of the ongoing Mayhill Road widening capital improvement project. Detour information can be found here, and signage is posted to alert motorists of the closure and detour in place.

Bonnie Brae Street
To accommodate mobility needs, this capital improvement project will expand Bonnie Brae St. from a two-lane undivided road to a divided four-lane road between Vintage Blvd. and I-35E. This project will also widen Vintage Blvd. from two lanes to a six-lane divided roadway from I-35W Frontage Rd. to US 377.

Bonnie Brae Street (See detour map)
This improvement project will include upgrades to the water lines in the area on S. Bonnie Brae Street from Highland Park to Willowwood Street as part of the North South Water Main Phase II captial improvement project. To allow crews to safely complete the improvements, a temporary street closure will be in place. Signage is posted to alert motorists of the temporary closure and detour in place during this time. 

Bonnie Brae Street
As part of the active multi-phase Bonnie Brae capital improvement project, crews are widening Bonnie Brae Street to a four-lane roadway from Roselawn Drive to just north of Vintage Boulevard. During this phase of the project, there are minimal traffic impacts as crews work are working outside of the roadway. Signage is posted to alert motorists of the construction in the area.

Bonnie Brae Street (See detour map)
As the Bonnie Brae Street capital improvment project progresses, the intersection of Bonnie Brae Street and Scripture Street is currently under construction for the installation of a roundabout, water, wastewater and drainage improvements. This phase of the project requires the interesection to be temporarily closed as crews complete the improvements. Detour information can be found here and signage is posted to alert motorists of the construction and temporary detour in place.

Fannin Street
Construction to improve the street and water services are planned to begin in the second quarter of 2020 from Welch to Beatty. 

Forrestridge Drive (See detour map)
This active project will include street reconstruction on Forrestridge Drive from Hobson Lane to Timbergreen Circle. Crews will verift the depths of utility lines in the area, barricade the failed sections of the pavement, replace the concrete (cufrb, valley gutters, driveways, etc.), remove eight inches of asphalt and base material, stabilize the subgrade, and install new asphalt. To allow crews to safely complete the construction, Forrestridge Drive from Hobson Lane to Timbergreen Circle will be temporarily closed to thru traffic.

Foxcroft Circle
Wastewater improvements from East of Old North to Emerson and Northcrest to Archer Trail are expected to begin in the fourth quarter of 2019.

Fulton Street
This ongoing project requires streets, water, and wastewater improvements from Congress to W. Oak. Work is currently underway to reconstruct the wastewater main from Congress to Gregg. This is the final phase of wastewater construction and street improvements will follow.

Greeenway/Augusta
Due to the deteriorating condition of the road, crews from the Streets and Wastewater Departments will begin improvements from Windsor Farms to the dead end in the first quarter of 2020. Signage will be posted to alert motorists of the temporary lane closure and parking restrictions.

Hercules Lane
This improvement project will include a water main replacement on Hercules Lane from Sherman Drive to Stuart Road. During this time, Hercules Lane will be closed to thru traffic while crews are present and reopened at the end of each work day. Weather permitting, crews are expected to complete the final phase of construction on Hercules Lane from Sherman Drive to Huntington Road mid-September.

Hickory Creek Road
The section of Hickory Creek Road between FM 1830 and Riverpass Drive underwent significant short-term improvements. This work included trimming trees to increase visibility and adding new guardrails, raised reflective pavement markers, new striping, and curve warning and guidance signs that illuminate when a vehicle approaches to improve safety. Review the latest project updates here.

Hickory Street 
The reconstruction of Hickory Street (Bonnie Brae to Carroll) is expected to be complete by fall 2019. The project includes upgrading the roadway, water, wastewater, gas, and electric utilities in the area. Crews recently completed street improvements from Avenue B to Fry Street, and a wastewater main replacement at the intersection of Fry Street. Street improvements have now progressed to Fry Street to Welch Street. Signage is posted to alert motorists of the temporary parking restrictions and construction. Please use caution when traveling in the area.

Highview Circle
This project includes street reconstruction on Highview Court from Forrestridge Drive to Forrestride Drive. Crews will verify the depth of utility lines, replace the damaged concrete (curb, valley gutters, driveways, etc.), remove seven inches of asphalt, and install new asphalt pavement. During this time, there will be no parking on the street and limited access to driveways while crews are present. 

Hill Alley
Water service improvements are scheduled to begin in the second quarter of 2020 from Robertson to Martin.

Hillcrest Street
This improvement project will upsize the wastewater main line and services for the area. Crews will also be installing new manholes to allow for better accessibility to maintain the pipes. During this time, there will be no parking on the street and traffic control will be in place on Hillcrest Street for the duration of the project. All residents will have access to their homes during this time.

Hinkle Drive (See detour map)
As part of the active Magnolia Drainage Project, crews began street and drainage improvements on Hinkle Drive from University to Windsor. To allow crews to efficiently and safely complete the improvments, Hinkle Drive is temporarily closed to thru traffic. During this time, all residents and businesses will maintain access to their properties via the detour route in place. Detour routes can be found here. Signage is posted to alert motorists of the temporary street closure and detour.

Kerley Street
This project includes improvements to the street, water and wastewater services from Duncan to Shady Oaks. Currently, crews from the Wastewater Department are replacing the sewer main, upsizing its capacity, and installing a manhole. All service lines in poor condition will be replaced and cleanouts will be installed at the right of way. During this time, a temporary street closure is in place from Duncan to Shady Oaks. Signage is posted to alert motorists of the temporary closure and detour in place.

Mayhill Road
To alleviate traffic congestion on Mayhill Road, this major City project will expand Mayhill from a two-lane undivided road to a divided four-lane road. Crews are currently working from US 380 to Edwards. 

McCormick Street
Beginning Monday, March 11, McCormick Street from Underwood Street to Avenue A will be closed permanently for construction. This closure will allow crews to begin utility work and construction of the new Fire Station 3 on the west side of McCormick Street. Underwood Street will remain open to Ave A and I-35E. Signage is posted to alert motorists of the closure and parking restrictions.

McKinney Street
As part of the active Mckinney Street widening capital improvement project, crews are installing a storm drain on Mckinney Streey from South Fork Drive to Grissom Road. To allow crews to safely complete the improvements, intermittent lane closures will be in place. A temporary signal light and/or traffic control flaggers will be in use when a lane is required to be closed. Street improvements will follow the storm drain installation. 

Mill Street
This project includes street, water and drainage improvements scheduled to begin in the fourth quarter of 2019 from Wye to Industrial.

Morse Street
This project will include the installation of a waterline as part of the ongoing Mayhill Road widening capital improvement project. Morse Street will be closed at the intersection of Mayhill Road to thru traffic to allow crews to safely complete construction. 

Mistywood Lane/Royal Lane
This active project requires street, water, wastewater and drainage improvements from Woodhaven to Jamestown including Royal and Rockwood. Crews are currently improving the drainage system from Rockwood to Jamestown. Water improvements are scheduled to follow in the second quarter of 2019. Signage is posted to alert motorists of the intermittent street closure and parking restrictions.

Mulberry Street
This street and water improvement project is from Bernard to Cedar and expected to begin in the fourth quarter of 2019.

Myrtle Street
As part of the active Locust Substation construction, Myrtle Street from Collins to Daugherty has temporary intermittent street closures in place. Signage is posted to alert motorists of the temporary closures and parking restrictions. 

Northwood Terrace
This improvement project will include new sewer and water main installations on Northwood Terrace from the cul de sac to Edgewood Place. During this time, temporary lane closures will be in place to allow crews to safely complete construction. Detours will be provided so residents maintain access to their homes. Crews will suspend the temporary lane closures from June 3 until June 19. During this time, residents will be able to safely travel in both lanes. Intermittent lane closures will be in place June 19 until the projects proposed completion date.

Orr Street
Street, water, and wastewater improvements are scheduled for Orr Street from Elm Street to Locust Street. Crews are currently replacing the water main, upgrading the water services, and fire hydrants on Orr Street. To allow crews to safely complete the improvements, one lane of Orr Street is temporarily closed during working hours and will reopen at the end of each day. Signage will be posted to alert motorists of the lane closures and parking restrictions. 

Panhandle Street
Street resurfacing and curb and gutter replacements are scheduled to begin in the fourth quarter of 2019 from Aileen to Malone. The process starts with the replacement of failed curb and gutter, driveway, radius, and valley gutter. Crews will follow with milling the old asphalt surface and apply new asphalt. Signage will be posted to alert motorists of the temporary lane closure and parking restrictions. 

Quail Ridge Drive
This project includes street and water improvements scheduled to begin in the fourth quarter of 2019 from Cooper Branch to La Paloma. 

Roberts/Woodland/Brown
Street and water improvements are scheduled to begin in the fourth quarter of 2019 on Roberts (from Brown to Brown) and Woodland (from Brown to Cherrywood) Signage will be posted to alert motorists of the lane closure and parking restrictions. 

Robson Ranch
Wastewater improvements from the easement between Robson Ranch and I-35W are scheduled to begin in the fourth quarter of 2019. 

Sagewood Street
This street improvement project from Meadow Lane to Pear Tree Place is expected to begin in the second quarter of 2020. 

Sandy Creek Drive
Wastewater improvements are underway on Sandy Creek Drive from Angelina Bend to Angeline Bend. To allow crews to safely complete the improvements, one lane of Sandy Creek Drive is temporarily closed during working hours and reopened at the end of each day. Signage is posted to alert motorists of the temporary lane closure and parking restrictions. 

Scripture Street
This street improvement project from Thomas to Jagoe is schduled to begin in the fourth quarter of 2019.

Sheraton Road
This project includes street reconstruction on Sheraton Road from Sun Valley to Hercules. Crews will verify the depth of utility lines, replace the damaged concrete (curb, valley gutters, driveways, etc.), remove seven inches of asphalt, and install new asphalt pavement. During this time, there will be no parking on the street and limited access to driveways while crews are present.

Third Street (See detour map)
This improvement project includes the replacement of failed curb and gutter, driveway, valley gutter, and street resurfacing on Third Street from Bolivar Street to N. Elm Street. During this time, Third Street will be temporarily closed to traffic during work hours and reopened at the end of the day. Motorists are reminded to use caution when traveling in the area and refer to the detour route for alternate routes

Thomas Street
This street improvement project is scheduled to begin in the third quarter of 2019 from Panhandle Street to W. Oak Street. Crews will be improving the quality of the street and signage will be posted to alert motorists of closures and parking restrictions.

Uland Street
This project includes street and wastewater improvements from Railroad to Rose. Crews are scheduled to begin these improvements in the first quarter of 2020.

Wainwright Street (See detour map)
This project includes sewer main improvments and the installation of a manhole on Wainwright Street and Prairie Street as part of the ongoing Pecan Creek Tributary 4 (PEC 4) Drainage Improvement Project.

Wellington Drive
Wastewater improvements northwest of Sherman are scheduled to begin in the third quarter of 2020.

Westgate Drive
Street improvements are expected to begin in the third quarter of 2019 from Fladger to Windsor.

Whitney Court
Street improvements along the full extent of Whitney Court are scheduled to begin in the first quarter of 2020. Signage will be posted to alert motorists of the temporary street closure and parking restrictions.

Windsor Drive
This street improvement project from Hinkle to Elm is scheduled to begin in the fourt quarter of 2019.

Williams Street (See detour map)
This improvement project will include the replacement of failed curb and gutter, driveway, radius, valley gutter, sidewalks, and street resurfacing on Williams Street from W. Oak Street to W. Hickory Street. During this time, Williams Street will be temporarily closed to traffic during work hours and reopened at the end of the day. Motorists are reminded to use caution when traveling in the area and refer to the detour route for alternate routes.

Yellowstone Place
This project includes street, water and wastewater improvements from Kings Row to Monterrey. Currently crews are completing sidewalk repairs. During this time, one lane of Yellowstone will be temporarily closed while crews are present and reopened at the end of each day. Signage will be posted to alert motorists of the temporary closure and parking restrictions.